Colony 2- Paving Updates 5/5

Phillips Paving has decided not to pave Halsey- Phase 1 (yellow) today due to the rain changes. They will try to mill phase 3 (green) instead.

Please review the following schedule. Any changes/updates will be made later this afternoon.

Phase 1 (yellow) May 6th

Phase 2 (red) May 9th

Phase 3 (green) May 10h

Phase 4 (blue) May 11th

Phase 5 (pink) May 12th

Phase 6 (turquoise) May 13th