Colony 1- Street project work week of 4/11 & 4/18
Please find below the scheduled work to be performed during the weeks of April 11 and April 18.
Scheduled events are subject to change based upon weather.
Week of 4/11
Monday
Mill and Prep- Blue
Tuesday
Mill and Prep- Blue & Purple
Wednesday
Mill and Prep- Purple & Orange
Asphalt - Pave Blue
Utility - Demo
Thursday
Mill and Prep- Orange
Asphalt- Pave Purple
Utility- Install Pipe and Concrete
Friday
No work
Week of 4/18
Monday
Asphalt- Pave Purple
Tuesday
Asphalt- Pave Orange
Wednesday
Asphalt- Pave Orange
Thursday
TBD
Friday
TBD