Colony 1- Street project work week of 4/11 & 4/18

Please find below the scheduled work to be performed during the weeks of April 11 and April 18.

Scheduled events are subject to change based upon weather.

 Week of 4/11                  

Monday   

Mill and Prep- Blue

Tuesday  

Mill and Prep- Blue & Purple 

Wednesday 

Mill and Prep- Purple & Orange     

Asphalt  - Pave Blue

Utility - Demo

Thursday   

Mill and Prep- Orange 

Asphalt- Pave Purple  

Utility-   Install Pipe and Concrete       

Friday

No work

Week of 4/18                  

Monday

Asphalt- Pave Purple            

Tuesday   

Asphalt- Pave Orange    

Wednesday

Asphalt- Pave Orange      

Thursday     

TBD         

Friday

TBD

    

 